Image: Ag-Grid Energy · Original source.
Renewables and heat reuse
Lent Hill Ag-Grid Digital uses electricity from manure and food-waste digestion to supply a flexible mining container. The operator reports a 300 kW grid-export limit alongside a 1 MW mining unit.
- Project at a glance
- 1 MW mining unit · 300 kW export limit
- Source date and context
- Operational from October 2024
- Published financial detail
- The sources reviewed do not include full project accounts.
- Our comparison
- A UK example per 1,000 miner kWh
About 5 minutes to read
A farm with more gas than it could export
Lent Hill has a practical problem that will be familiar to some farm generators: it can produce more energy than its grid connection allows it to sell. Ag-Grid reports a 300 kW export limit and a separate 1 MW mining unit. The miners provide another outlet for electricity at the farm. Their load can rise or fall with generation, giving the operator an alternative to leaving some of the biogas unused.
“By directing the excess power to crypto mining, we are able to reduce the biogas going to the flare.”
Where the farm electricity goes
The farm still needs power for its digesters, pumps and other equipment. Only the electricity left after those uses belongs in the mining calculation. Heat from the CHP engine may already keep the digestion process running, so it should stay in the farm's existing heat account. The source does not describe recovery of heat from the miners.

What the numbers could look like in the UK
The calculation below uses assumed UK prices to show how the costs fit together. It is our example, not this project’s reported earnings. Replace the inputs with current machine estimates and the costs at your own site.
Illustrative UK calculation
Income and running costs
1,000 kWh used by miners, plus 50 kWh for pumps and fans. All amounts in pounds.
Operating contributionBefore equipment and installation costs
£15.901.59p per miner kWh
Here, using the electricity for mining gives up a 5p/kWh export payment. That cost includes the 50 kWh used by pumps and fans. It is the value of an alternative sale, so it is not also charged as a grid electricity bill. The example assumes the generation equipment already exists.
| Mining income | 8p per miner kWh; an assumed rate, not a live earnings estimate |
|---|---|
| Electricity | 5p/kWh × 1,050 kWh = £52.50 |
| Pool fee | 2% of gross mining income |
| Useful heat | 0% of miner electricity = 0 kWh; no heat income assumed |
| Other running costs | £10 per 1,000 miner kWh; an allowance to replace with your own costs |
| Costs still to add | Equipment, installation, finance, tax, depreciation, major replacements and any costs above the allowance |
The contribution is what remains from mining income and useful heat after the stated running costs. It is not net profit: the equipment and other excluded costs still have to be recovered. Pumps and fans use electricity but earn no mining income in this calculation.
| Gross income per miner kWh | Operating contribution |
|---|---|
| 5p | −£13.50 |
| 8p Chart example | £15.90 |
| 11p | £45.30 |
- Mining income needed to cover running costs
- 6.38pper miner kWh
- Highest electricity cost or export value supported
- 6.51pper total electricity kWh
These are two ways to read the same example. Adding equipment costs or a larger maintenance allowance raises the income needed and reduces the electricity price the project can afford.
Compare heating options and work out annual costs
If the electricity has no export value or other useful destination, removing the export cost improves this example by £52.50. Generator maintenance, equipment costs and any payment to the electricity owner still remain. Heat is given no value here because the source does not establish a usable heat supply.
For an annual estimate, use the miner electricity expected during hours when running makes sense. Scale the contribution by annual miner kWh divided by 1,000, then deduct fixed annual costs. Recalculate if electricity prices, mining income or usable heat change.
Simple payback is the total installed cost divided by positive annual cash contribution. There is no payback under a scenario with zero or negative contribution. The sources reviewed here do not provide the full project accounts needed to calculate an actual payback for this installation.
Start with the export limit
Separate engine output, site demand and permitted export when sizing a flexible load.
Meter engine output, digester consumption, site demand, export and mining on matching intervals. Confirm which asset is actually mined and which party owns it.
Questions worth asking
- What changes if the export limit is relaxed?
- Does the agreement pay the farm a fixed energy price or a share of mining income?
Try your own electricity and heat figures
Compare available miners and dated earnings estimates. Include heat only where you can use it or have a customer for it.
Sources and photographs
Sources checked on 29 September 2026. Project facts and quotations come from the publications below; the UK calculations and practical assessment are The Mining Shop’s analysis. This article is based on published material, rather than a site visit.
Photographs: Ag-Grid Energy (source).





Join the ASIC Mining Discussion
Members can read and join the discussion
Log in to read comments from other miners. Create a free account if you would like to ask a question or share your experience.
Membership helps us protect the discussion from spam and keep answers useful.