Skip to main content
£0.00 0

Basket

No products in the basket.

MINING BUNDLE

568x Antminer S21 319TH + 2x ANTSPACE HW7 Container · T-type

SHA-256 · 181.19 PH/s

568 miners · Hydro cooling · With container

Pre-Order
ANTSPACE HW7 2MW Mining Container — unit 1 of 2ANTSPACE HW7 2MW Mining Container — unit 2 of 2
Antminer S21 — 568 included

Catalogue preview — this bundle is not available to order yet.

Hashrate
181.19 PH/s319 TH/s each
Algorithm
SHA-256
Efficiency
16W/TH
Power
2.9MW5.1kW each
Miner Load
2.9MWAuxiliary power pending
Earns/kWh
Pending
Solo · eCashAuto · Annual comparison
Equipment Price
£1,444,410.00Ex VAT£1,668,740.00

Total Saving £224,330.00

£2,073,082.84₿33.16421060 equivalentGross Payback

Component Miner Rankings

Component miner ranking #51
568x Bitmain Antminer S21 Hydro 319Th SHA-256 Bitcoin MinerOverall #51 · Earnings #154 · Efficiency #187 · Value #58 · ROI #76

These are the included individual miners’ existing ranks. Bundle economics use the complete configuration price, delivery, discount and auxiliary power. Mixed fleets show an average component percentage score, with the individual ranks in its breakdown.

Selected Equipment Schedule

568 miners · Pending operating load. Only the following quantities and products are included in this configuration.

EquipmentQuantityRole
Bitmain Antminer S21 Hydro 319Th SHA-256 Bitcoin Miner568Miner
Bitmain ANTSPACE HW7 2MW Hydro Mining Container2Infrastructure

Container Layout · T-type.

Container Planning & Headroom

Provisional maximum per container: 284 miners, in 2 equal groups. Quantities allow 5% above listed miner power and reserve 10% of reference cooling and electrical capacity, and of flow where published. This is a planning allowance, not installation approval.

Miner Design Load
1.52MW
Auxiliary Electrical Allowance
255kW
Cooling Headroom
317.99kW
Coolant Flow Allowance
170.40 m³/h

Auxiliary allowances are conservative design bounds, not average electricity consumption. Running costs remain unconfirmed until the complete load schedule is supplied.

Normal stock operation, no overclocking. Hydro inlet at or below 35 C. Site ambient, fluid, pressure, branch circuits and delivered revision require confirmation.

Use the standard 2100kW value as the planning ceiling, not the 2500kW maximum. Budget separate no-load container/tower bounds of 160+95kW; possible overlap and concurrent draw remain unresolved. Only the container 160kW bound is charged to the liquid circuit. Two independent cooling sides.

Individual Miner Connection

The miner maximum input current is within the published bay reference. Confirm the delivered connectors, protection, voltage and revision.

Miner Maximum Input
12A
Published Bay Reference
14.5A

Miner electrical specification

Manufacturer Equipment Reference

Container with two distribution cabinets, four supply circuits and two cooling circuits; matched 2000kW dry tower (1000kW per side), pumps and controls. The reference input is AC380–480V, 50/60Hz; individual miner and branch requirements still apply.

Outstanding Supplier Checks

  • Confirm the delivered T-type or 2U-type revision and priced tower, pumps, pipework, controls and coolant schedule.
  • Reconcile the 160kW container and 95kW tower limits; neither is a measured complete operating load.
  • S21 Hydro 319TH is rated 12A maximum, within the 14.5A bay reference; exact connectors/protection still need confirmation. S23e U2H specifies 20A maximum, LP34 power and UQD08 coolant connectors, requiring its matched 2U branch revision. Reducing fleet size does not resolve branch compatibility.
  • Confirm cooler duty at the site ambient and fluid temperatures; the water-curtain table has inconsistent temperature notes.

Manufacturer reference

Price Breakdown & Volume Discount
Miner Subtotal
£1,381,944.00
Infrastructure Subtotal
£172,200.00
Miner Discount
15%
Recorded AER Delivery Allowances
£114,600.00

The volume discount applies once to current published miner prices, including their embedded delivery allowance. Freight enters the complete package total once. Infrastructure is not discounted. Existing AER £10 rounding applies. Unconfirmed amounts are indicative, not an orderable offer.

Power Consumption & Installation Requirements

Miner Load
2.9MW
Auxiliaries
Unconfirmed
Known Load Only
2.9MW
Energy per 24 Hours
69,577.728kWh

Miner-only consumption is shown while auxiliary power is unconfirmed. Pumps, fans, controls and other site loads must be added; this is not a complete operating total.

Mining Earnings & Block Odds

Scenario, odds & assumptions

Constant-condition scenario, not a forecast. 100% operating time, £0.000/kWh, 2% pool service fee and 0% Solo service fee. Fees are editable assumptions; confirm your chosen provider’s charges. Network transaction rewards are included in the shared source estimate.

Operating power Pending includes Pending auxiliaries. Miner quantities are fixed. Auxiliary inputs must cover the listed cooling equipment.

Bitcoin equivalent is a display conversion of the selected mining routes, not a claim that the hardware mines Bitcoin. Recorded Bitcoin price £62,509.64 at 2026-10-21T11:08:16+00:00.

Auto selects the highest expected annual return after the entered fees and operating electricity for each algorithm. Equipment cost is fixed for the selected configuration. A higher expected Solo return does not mean a reliable payout.

eCash Expected Blocks / Year
228,699.080774
At Least One Block
≈100%
No Blocks
<0.0001%
Block Value
£9.06

Block probabilities use this fleet’s actual hashrate over the selected timeframe. Fractional expected blocks are a statistical average, not part of a block paid to you.

Excludes hosting, maintenance, taxes, finance and other operating charges not explicitly entered. Prices, difficulty, rewards and uptime can change. Network inputs: . Calculated .

Annual alternatives after mining fees, before shared electricity costs
Asset / ModeExpected Earnings
SHA-256 · eCash · Solo£2,073,082.84
SHA-256 · Quai · Solo£2,036,742.08
SHA-256 · Bitcoin Cash · Solo£1,915,411.95
SHA-256 · Fractal Bitcoin · Solo£1,911,317.70
SHA-256 · Bitcoin Cash · Pool£1,892,268.16
SHA-256 · Bitcoin · Solo£1,866,838.06
SHA-256 · eCash · Pool£1,859,859.37
SHA-256 · Fractal Bitcoin · Pool£1,796,257.12
SHA-256 · Bitcoin · Pool£1,788,560.03
SHA-256 · Bitcoin · Pool£1,785,319.16
SHA-256 · Quai · Pool£1,747,238.83
SHA-256 · DigiByte · Solo£1,351,329.63
SHA-256 · DigiByte · Pool£1,344,964.73

Equipment Scope & Site Requirements

The selected equipment schedule itemises the miners and container(s). Manufacturer system reference: Container with two distribution cabinets, four supply circuits and two cooling circuits; matched 2000kW dry tower (1000kW per side), pumps and controls. The reference input is AC380–480V, 50/60Hz; individual miner and branch requirements still apply. The saved price record does not independently confirm the supplied packing list. Final tower, pump, controls, pipework, miner connections and coolant inclusions require supplier confirmation.

Site works, upstream electrical supply, networking, commissioning, maintenance and any equipment not itemised.

Availability

This configuration is a draft and is not available to buy yet. The included equipment, pricing and stock must be complete before it is listed for sale.

Outstanding Configuration Checks
  • State auxiliary power and reserve explicitly.
  • Complete-package delivery allowance is missing.
  • Infrastructure capacities need verification.
  • Auxiliary load must include the infrastructure auxiliaries.
  • Itemise the complete auxiliary load, including pumps, fans, coolers and controls.
  • The complete auxiliary schedule must match the reviewed per-module loads; external loads cannot bypass module capacity checks.
  • Electrical supply capacity is missing.
  • Record the installation electrical reserve explicitly.
  • Exact equipment fit and installation design need confirmation.
  • Record the reviewed electrical design and its evidence.
  • Record the reviewed cooling design and its evidence.
  • Record the reviewed ancillaries design and its evidence.
  • No valid per-module placement was found for the fleet and cooling limits.
  • Planning headroom is provisional; confirm the supplied revision, site conditions and complete auxiliary schedule before installation approval.
  • The component specification or price changed; review this package.